New Kitchen Before Christmas? Here's What to Know
Every autumn we get the same question. Someone has decided this is the year the kitchen finally gets sorted, usually because they are hosting Christmas, or because they took one look at it last January and promised themselves it would not happen again. The question is always some version of "can we actually get this done in time?" 
 
The honest answer is that it depends entirely on when you are asking. Here is the realistic timeline, so you know exactly where you stand. 

Work backwards from the big day 

A full kitchen renovation, from your first visit to us through to the last cupboard door being hung, typically breaks down like this: 
 
Design and planning: one to two weeks, sometimes longer if you are still deciding between layouts 
Order and manufacture: four to eight weeks, depending on the range and supplier 
Installation: one to two weeks on site for most kitchens, longer where there is significant plumbing, electrical or structural work involved 
 
Add it up and a straightforward kitchen realistically needs eight to twelve weeks from your first conversation with us to the last fitting being tightened. That means if you want to be cooking Christmas dinner in a finished kitchen, the ideal time to have your first design appointment is September to October. 
 
If you are reading this in November, it is not too late, but your options narrow. Certain ranges hold shorter lead times than others, and a smaller job like new doors and a worktop on existing carcasses can move much faster than a full strip-out. We will always tell you straight whether Christmas is realistic once we know what you are working with, rather than promising a date we cannot hit. 

What decides whether you make it 

How much you are changing. Swapping doors, handles and a worktop on units that are structurally sound can be turned around in a fraction of the time of a full renovation. Moving a sink, changing the layout, or knocking through a wall adds weeks, not days, because of the plumbing, electrical and building work involved. 
 
How quickly you decide 
The single biggest delay we see is not manufacturing, it is indecision. Every week spent going back and forth on a worktop colour is a week off your installation slot. If Christmas is the deadline, come to the first appointment with a rough idea of style and budget already in mind. 
 
Trade availability 
Anything needing plastering, gas work or significant electrical changes depends on those trades having a slot free. We manage all of this in-house rather than subcontracting piecemeal, which is one of the reasons we can usually move faster than a job coordinated across separate trades. 
 
The range you choose 
Some kitchen ranges are held in more depth of stock than others. If the calendar is tight, tell us that upfront and we will steer you towards ranges with realistic lead times rather than the one that happens to catch your eye in the showroom. 

Why September / October is actually the ideal time to start, not just the deadline 

Beyond the maths above, there is a genuine advantage to renovating in autumn and winter rather than waiting for spring. 
 
Trades are generally quieter between late September and February than they are in the traditional spring and summer renovation season, when everyone books at once. That usually means more flexibility on start dates and less waiting around for a fitting slot to open up. You are also less likely to be relying on outdoor space or an external door being open for long periods, which matters less in winter than it sounds, since most of the disruption from a kitchen fit happens indoors regardless of the weather. 
 
The other advantage is simply psychological. Starting in September / October means you are not living through the disruption during the run-up to Christmas itself. The mess, the takeaways, the makeshift kettle-and-microwave setup in the dining room, all of that happens now,September and by December you are settling into a finished kitchen rather than still waiting for it. 

What to do this week if Christmas is the goal 

Book a design appointment now. Come to the showroom or arrange a home visit. The earlier we can survey your space, the earlier a realistic timeline gets locked in. 
 
Set a budget range before you arrive. It saves time in the first meeting and means we can show you ranges that fit rather than everything on the floor. 
 
Decide what you are prepared to compromise on. If the deadline matters more than the exact worktop, tell us that. We can usually find a way to hit a date if we know that is the priority. 
 
Ask directly whether your chosen range can be delivered in time. Not every kitchen range moves at the same speed, and we would rather tell you that on day one than at week six. 

Frequently asked questions 

Is it too late to get a new kitchen before Christmas? 
If you are starting in October, a straightforward kitchen is realistic. Starting in November narrows your options to faster-turnaround ranges or smaller-scope work like a door and worktop makeover. Come and talk to us and we will give you a straight answer based on your actual kitchen. 
 
How long does a full kitchen installation take once it starts? 
Most installations take around one to two weeks on site, depending on how much plumbing, electrical and building work is involved. 
 
Can a kitchen makeover be done faster than a full renovation? 
Yes. Replacing doors, handles and worktops on existing carcasses avoids most of the lead time that comes with manufacturing entirely new units, and can often be turned around in a couple of weeks. 
 
Is winter actually a bad time to renovate a kitchen? 
No. Trades are generally quieter than the spring and summer rush, and the work itself happens indoors regardless of the season. 
 
What is the first step if I want to start now? 
Book a design appointment at one of our showrooms in Bedworth, Rugby or Hinckley, or arrange a home visit. We will survey your space and give you an honest timeline before anything is ordered. 

Ready to get started? 

If Christmas is the target, the best thing you can do today is get a design appointment in the diary. Visit us at Bedworth, Rugby or Hinckley, or get in touch and we will tell you straight away whether the timeline works. 